What to Check in Prefabricated Substation Factory Acceptance?

Easysail Transformer Published

When purchasing a prefabricated substation, the factory acceptance test (FAT) scope, witnessing method, passing criteria, and delivery documents should be agreed upon before contract signing. Buyers should verify test documentation for the transformer, high-voltage switchgear, low-voltage switchgear, and accessories, and confirm factory inspection items for whole-station assembly, interfaces, and agreed functions. Whether the quotation includes witnessing, rectification re-inspection, and pre-shipment documents should also be clearly stated to avoid discrepancies during delivery.

What is the Difference Between FAT and Equipment Testing?

FAT is a factory acceptance activity arranged according to the contract, and repeated or witnessed tests are executed as agreed. Routine test records for transformers and switchgear correspond to the delivered equipment, while type test data are typically used to prove that relevant designs or product series meet specified requirements.

Buyers should distinguish three things: which are equipment routine test reports, which are existing type test data, and which are whole-station inspections required by the contract to be witnessed at the factory or conducted separately. Specific items and judgment criteria are subject to the contract and applicable standards.

What Scope Should Be Verified in Whole-Station Acceptance?

Buyers can verify the equipment configuration, packaged assembly, and interfaces of the box-type substation according to the contract checklist:

  • Transformer model, capacity, voltage, and cooling configuration.
  • Models, circuits, and main components of high-voltage and low-voltage switchgear.
  • Busbars, cable interfaces, metering protection, and auxiliary power supplies.
  • Enclosure dimensions, protection requirements, markings, and accessory quantities.
  • Layout, wiring, and interface data consistent with approved drawings.
  • Functional inspection records for mechanical interlocking, control, signaling, etc., as specified by the contract.

Select applicable inspection items based on the prefabricated substation structure and project technical agreement.

How to Agree on FAT Witnessing and Costs?

Before quotation, confirm whether the buyer will witness, whether on-site witnessing or remote witnessing will be adopted, as well as the witnessing notice, schedule, and participating parties. Also, specify testing equipment, test records, report language, and submission time.

State clearly whether routine tests are included in the main body quotation, and agree on the responsible party for the costs of special tests, third-party witnessing, repeated testing, and rectification re-inspection. The manufacturer assumes product quality responsibility in accordance with the contract.

What Documents Should the Buyer Request?

It is recommended to list the following in the procurement technical attachments:

  • Approved single-line system diagrams, layout drawings, and interface drawings.
  • Equipment list, key component models, and serial numbers.
  • Routine test reports for transformers and high/low-voltage equipment.
  • Type test data and special test records required by the contract.
  • FAT procedures, checklists, result records, and punch lists for open issues.
  • Operation and maintenance documents, spare parts list, and packing data (as per contract).

If the reports do not match the models, rated parameters, or test conditions, the supplier should be requested to explain and supplement them before shipment. Acceptance records should indicate the drawing version. If equipment replacement or interface changes occur after approval, please confirm in writing whether the affected inspection items and reports need to be updated.

How to Compare FAT-Related Quotations?

First adjust each supplier's quotation to the same supply boundary, then compare prices. Focus on whether the whole-station main body, component brands and models, accessories, tests, witnessing, documentation, and packaging are listed separately. A quotation that appears lower may not include remote witnessing, specified testing, or export packaging.

Contracts should also clearly state acceptance issue handling, re-inspection procedures, release conditions, and document handover milestones. At the same time, responsibilities and delivery milestones for factory acceptance and installation/commissioning acceptance should be listed separately.

What Else Must Be Confirmed Before Shipment?

Before shipment, verify the nameplate, equipment serial number, packing list, accessories, dimensions and weight, transportation split plan, and protective packaging requirements, and confirm the agreed FAT records and pending issue handling status. Delivery locations, trade terms, transportation responsibilities, and warranty commencement methods should also be consistent with the contract.